Sample Project · G+2 Residence
4,800 sq ft · RCC framed · Started 12 Mar 2026 · Handover 31 Jan 2027
ON TRACK
SAMPLE DATA
← Back to website
Overall progress
62%
Planned 60% by today
Budget spent
₹48.6L
of ₹78.0L approved
Days to handover
96
Target 31 Jan 2027
Next payment
₹9.4L
Due 05 Nov · Roof slab stage
Open issues
3
1 approval · 2 site items
Progress: planned vs actual
Planned
Actual
Work stages
% COMPLETE
Payments
₹ LAKHS
Advance
12 Mar
7.8
PAID
Foundation
20 Apr
11.7
PAID
Ground floor slab
02 Jul
11.7
PAID
First floor slab
28 Aug
9.4
PAID
Roof slab
05 Nov
9.4
DUE
Milestones
3 OF 6 DONE
Approval
Mar
Foundation
Apr
GF slab
Jul
Roof slab
Nov
Finishing
Dec
Handover
Jan
Site visits
LATEST
Roof slab shuttering checked
24 Oct · Engineer visit
OK
Steel spacing corrected, grid C
22 Oct · Quality check
FIXED
Brickwork 1st floor 80% done
19 Oct · Progress
OK
Needs attention
3 OPEN
Choose floor tiles
Owner decision · by 10 Nov
OWNER
EB service connection
Application pending
APPROVAL
Cement stock below 2 days
Reorder 200 bags
MATERIAL
Site photos
24 OCT